NB Power has officially signed an agreement with the Mactaquac Improvement Partnership to move forward with the civil work component of the Mactaquac Life Achievement Project (MLAP). This major milestone is a critical step toward ensuring the generating station remains a reliable source of electricity for Saint John and the rest of New Brunswick for decades to come.

The Mactaquac Improvement Partnership
The newly formed agreement is with a consortium known as the Mactaquac Improvement Partnership, which includes industry leaders Aecon, FlatironDragados, and Green Infrastructure Partners. This collaboration brings together extensive expertise in large-scale infrastructure projects to tackle the complex rehabilitation of the Mactaquac Generating Station.
Development Phase and Timeline
Currently, the agreement covers a 12-month development phase. During this time, the contractor will work closely with NB Power to finalize designs, establish firm schedules, and develop accurate cost estimates. It is important to note that this phase does not authorize the start of construction. Subject to regulatory approvals, government review, and the successful completion of this planning stage, actual construction is projected to begin in mid-2027.
Securing Our Energy Future
The MLAP is designed to rehabilitate the existing station by addressing the deterioration of its concrete structures and upgrading critical systems, including turbines and generators. Preparatory work and product testing are already underway at the site to prepare for these major project activities.
“New Brunswickers expect us to make careful, informed decisions about major investments in our electricity system,” stated Lori Clark, President and CEO of NB Power. “This agreement allows us to do the planning work necessary to better understand costs, schedules and risks before any final decision is made. It is a responsible step that supports good decision-making and governance, and helps ensure we continue providing reliable electricity for customers for decades to come.”
For more details on this development, you can read the full update on the NB Power official website.
Frequently Asked Questions
What is the Mactaquac Life Achievement Project (MLAP)?
The MLAP is a major infrastructure project aimed at rehabilitating the Mactaquac Generating Station. It involves repairing deteriorating concrete structures and upgrading essential equipment like turbines and generators to extend the station’s operational life.
When will construction begin?
Construction is tentatively scheduled to begin in mid-2027, pending the successful completion of the current 12-month development phase, government review, and necessary regulatory approvals.
Who is involved in the Mactaquac Improvement Partnership?
The consortium consists of Aecon, FlatironDragados, and Green Infrastructure Partners, who will work alongside NB Power during the development and potential construction phases.